Project Background:
After many, many years of planning and preparation the missing mile of bike trail in Homewood is going to be built. TCPUD is excited to complete this critical section of trail, providing continuity and improved safety for our trail users from Tahoe City to Sugar Pine State Park.
Project Details:
The approximate 1 mile of trail will be constructed between Cherry St. to the north and Fawn St. to the south, completing the missing link on the West Shore Trail. Construction activities will be located along the Highway 89 right-of-way westerly shoulder and along the Placer County roads of Silver St., Sans Souci Terrace, and Trout St. Temporary construction traffic controls will be implemented throughout construction with minor impact to vehicle traffic.
Construction Time Frame:
Construction is scheduled to begin the week of May 9th and will be completed this fall.
If you have questions or concerns, please do not hesitate to contact us at the TCPUD Main Office: 530-583-3796.